Oldhamstocks Village Hall Redevelopment Group – Report on Work Undertaken – November 2019

With only four remaining members, the Oldhamstocks Village Hall Redevelopment Group is of the opinion that it has reached as far as it can and that the purpose, membership and remit of any future village hall working group will need reviewed in order to make further progress, towards developing options for the new hall. The Group has therefore produced a summary report of work done to date.

OVHRG Final Summary Report November 2019

The OCA Committee Would like to thank the Oldhamstocks Village Hall Redevelopment Group for all of the hard work they have put in to progress the new hall.

 

OCA Committee Hall Update

This newsletter gives an excellent summary of options that the OCA Committee explored for a new village hall.  This highlighted work that was done to reduce the cost of the Simpson and Brown design to a build cost of £577k and hence a estimated cost which include contingency, inflation, professional fees and VAT on fees, to £674k

OCA Newsletter June 2018

The early years

As far back as the late 1970’s there were problems maintaining the hall roof and windows. In 1996 the Committee applied for national funding to rebuild the hall stating ” The present hall is of a wooden construction and was purchased second hand from the MOD Circa 1952 and is now somewhat worse for wear.

Continue reading