It’s been a relatively quiet week. While the concrete of the foundations is now set and level, we have a bit of a pause while the final tweaks are done to the design of the steel frame. This comes after the steel company came to site to scan the final real position of the foundations for tolerance checks. All approved, and progress is being made behind the scenes for steel going up in the next 2 or 3 weeks! In the meantime, SPEN have been on site again and we have the (third…) final junction box in place for the build team to take their power from. Our architects from CSY joined OCA and TRF on site for a slightly soggy monthly progress meeting…!