Highlights: TRF are back on the village hall site and are getting started on digging trenches for the foundations of the new hall. OSCR have changed their advice to us as to how to wind up the original OCA charity, which means considerable work has been wasted, but we are advancing with a new approach. A date for the OCA and OCA SCIO AGMs has been put forward.
Minutes
Committee meeting, November 4th 2025
Highlights: Agreed to buy a storage container to hold contents of the old hall through the build. This will be stored at Ferneylea to save space and damage to the green. Conversations with ELC ongoing regarding the playground equipment. Some can be moved and reused, but not all. Committee agreed to continue funding the good work done by Oldhamstocks For Nature.
Committee meeting, October 5th 2025
Highlights: Land purchase finally complete! Discussions with CWPEnergy on monies available immediately and in future. Farewell event for the old hall being planned.
Committee meeting, September 28th 2025
Highlights: The Ridge returned a second revision of costing details for the hall build. Pressing for final closure of the land purchase. Village hall requires a postal address for SPEN to disconnect the power! Planning for a farewell event for the old village hall.
Committee meeting, September 21st 2025
Highlights: Seeking final written funding agreement from CWP Energy. Unfortunately, the CARES funding for our renewables is no longer available, thanks to a change of government policy. Final project costs including all areas of spending has been totalled up.
Committee meeting, September 14th 2025
Highlights: OCA meetings are moving from monthly to weekly during the most intensive period of work towards the new hall. Final funding discussions are under way with CWP Energy. Land purchase is now all but complete – monies are being transferred to our solicitor to make payments. Stage 2 of hall cost refinements with The Ridge is underway.
Committee meeting, September 2nd 2025
Highlights: Defibrillator on the village hall has been provided with new paddles and is back in service. Bus stop has been agreed to be replaced by ELC with something in keeping and more accessible. After all tender responses for the hall have been received and reviewed, The Ridge Foundation is tentatively selected as our preferred contractor for the build!
Committee meeting, August 5th 2025
Highlights: Tender responses received for 4 of the 5 contractors, 1 still to come. Decision on the mandatory EV chargers is now critical for progress towards the hall build. Oldhamstocks For Nature doing lots of good work around the village!
Committee meeting, July 7th 2025
Highlights: Planning Conditions for the hall include providing 2 EV charging stations, the location for which has to be decided and confirmed with ELC before the hall build can commence. SORELL report that the deadline for representations to ECU regarding Springfield solar farm is 4th August.
Committee meeting, June 3rd 2025
Highlights: Land purchase for the hall is moving to final stages, with all terms now agreed. Tender documents for the hall build have been sent out to 5 contractors!
