The lights are on! Ok, so they’re temporary lights for TRF to work by indoors, but it does mean we have enough “indoors” to need lights and enough roof to keep them dry!
This week, we have the first elements of the final roofing gone on. At the back of the building, we have a very fancy zinc gutter now running the whole length of the building. (Just in time for a horrible weekend’s weather, even if there’s no downpipes yet…)
At the front, the majority of the roof is now boarded up with plywood. Next week, the main sheets of the final roofing should start to go on, beginning at the back.
Work still continues inside too. More insulation has been fitted into the timber frame and panelled over.