Committee meeting, May 5th 2026

Highlights: Functional blockwork for the base of the hall walls has been completed, with the decorative front blocks now started. Borehole for the heat pump is to be drilled next week. GreenHeat assure us that there is no risk to neighbouring buildings. Committee discussed reinstating decorating stone panels on the front face of the hall. Committee agree to shorten OCA SCIO’s financial year for 2025/26 as a one-off action during the usual period of the hall build.

Meeting minutes 5.5.26