Hall Build – Week 18

A busy week for blockwork! Blocks for the three base courses all around the hall were delivered and largely installed this week. Extensions to foundations were completed and the steelwork bases were permanently sealed with concrete. Delivery was also taken of the decorative buff natural stone that will be the visible outer to the base layers of the wall below the final timber cladding.