Old hall farewell party!

With the build of the new hall rapidly approaching, time has finally run out for the old hall that has served so many people so well for so long. For some 70 years, the old military shed has hosted pub quizzes, weddings, flower shows, and lots more.

We needed to send her off with a celebration, so today, the community gathered there for one last time. With tables laden with home baking, and a fridge full of champagne, we raised a final toast to the old girl in glorious sunshine!

Tender replies received!

We have now received all six tender responses from the contractors we submitted to. CSY have managed to make a summary table of the responses, showing the quote breakdowns “like-for-like”.

We have been in touch with our primary funders, Community Wind Power, as clearly, their view on choice of contractor and total cost is critical. Unfortunately, the contractor that built Abbey St Bathans’ hall, who were already well known to CWP, declined to submit tender for the project. However, we have plenty of other local contractors that come with recommendations from our architects and other sources!

The next stage then, is to decide on a first-choice contractor with input from CWP. We will then work with the chosen contractor to refine their quote to be as close as possible to exactly what we want for the final build. 

A specialist asbestos handling company is booked to survey the existing hall at the end of this week. Getting this survey done now will speed the demolition along, no matter which contractor we go with in the end. If any asbestos is found, it will be safely removed by specialists. 

Village hall plans out to tender

CSY have gone to tender with 5 contractors

Five contractors, who expressed an interest in tendering for the demolition and construction of the new VH, have been sent a comprehensive tender document by our architects CSY.

All five are local to East Lothian and the Borders area.

OCA committee have already started holding site meetings with the contractors to ensure that they have all the additional information they need to produce their costed proposals.